|
Study of Interconnection and Competition in the Electricity Supply Sector in Hong Kong
Introduction
This paper sets out the key findings of a
consultancy study of Interconnection and Competition in the Electricity Supply
Sector in Hong Kong.
Background
2.Recognizing the global and regional trend and that a number
of long term issues will need to be addressed in future, Government commissioned
a consultancy in 1998 to conduct an independent Study of Interconnection and
Competition in the Electricity Supply Sector in Hong Kong as a first step. The
main objective was to establish whether additional interconnection between Hong
Kong's two electricity supply companies and encouragement of competition in the
electricity supply sector would be in the interests of consumers. The
consultants were specifically asked to carry out the following tasks in the
course of the Study-
| Task 1: |
Assessment of the potential costs, benefits and other
implications of increasing interconnection capacity between CLP Power
Company Hong Kong Limited (CLP) and The Hongkong Electric Company
Limited (HEC). |
| Task 2: |
Assessment of the potential for competition in the
electricity supply sector, evaluation of alternative market structures
and identification of the optimal market
structure. |
3.The results of the Study reflect the independent findings of
the consultants.
Consultants' Findings
Task 1 : Interconnection
4.Key findings are broadly set out below.
-
There is an existing interconnector with limited capacity
between CLP and HEC. Increased interconnection capacity is technically
feasible, although there may be some logistical and timing constraints which
need to be studied further.
-
Increasing the capacity of interconnection has certain
potential benefits. However, the benefits in Hong Kong compared to those
enjoyed by other interconnected systems elsewhere, would be limited because
of the similarities in the peak load profiles and generation plant types of
the two power companies.
-
Under the current Scheme of Control Agreements (SCAs),
which run to 2008, the Government cannot require the utilities to take steps
to construct increased interconnection capacity. Implementation of such a
requirement before 2008 would therefore be difficult to arrange without
voluntary acceptance by the utilities.
-
Under the least cost scenario analysed by the consultants,
whereby HEC and CLP systems were regarded as one system for the purpose of
planning for additional generation capacity, constructing substantial
additional CLP-HEC interconnection capacity would enable CLP generation
capacity to be used to support the HEC service area. Compared to the base
case which entails construction of additional generation capacity within the
HEC system in the near term, this option would bring overall economic
benefits equivalent to on average a reduction in tariffs of 0.4 cents/kWh in
the period up to 2008. The economic benefits however would not be evenly
distributed between customers of the two power companies. Compared to the
base case, HEC tariffs would decrease whereas CLP tariffs would increase.
-
There may be a risk that implementing increased
interconnection between HEC and CLP, deferring construction of additional
generation capacity and implementing joint plant dispatch in the near term -
which would deliver economic benefits by reducing costs and hence tariffs
under the SCA - may also have the effect of strengthening CLP and weakening
HEC from the point of view of future introduction of competition, and may
work against longer-term consumer interests. However, increased
interconnection capacity will eventually be necessary for competition and
technical reasons.
Task 2 : Competition
5.Key findings are broadly set out below.
6.There are several constraints in Hong Kong against the
introduction of competition in the electricity supply industry in the short
term. The key ones are -
-
The SCAs, which are structured for regulating individual
power utilities, are not compatible with the concept of competition. There
will be virtually no scope for competition with the SCAs remaining as they
are and with only two players in the market.
-
The transfer capacity of the existing 132kV interconnectors
is rather limited and therefore is not conducive to any meaningful
competition between the two power companies. Installation of large capacity
interconnectors is a pre-requisite for competition.
-
Electricity supply from the Southern China network may be a
potential source of economic electricity supply and may help bring
additional competition to the Hong Kong electricity supply sector in future.
However, until the electricity supply industry in the Mainland is
restructured, the prospect of having major new entrants into the Hong Kong
electricity supply sector will be rather limited.
7.The consultants have identified and assessed four types of
possible market structure, namely Vertically Integrated model, Single Wholesale
Purchaser model, Multiple Wholesale Purchasers model and Retail Competition
model. Hong Kong currently has in place the Vertically Integrated model, whereby
power companies undertake all activities, including generation, transmission,
distribution and retailing, in distinct service areas. The consultants consider
that, while consumer benefits may be realised from increasing the
interconnection capacity and operating power pooling arrangements, such changes
would not in themselves promote competition under this model. The other models
identified envisage, inter alia, separation of the generation business from the
transmission, distribution and retailing business, the operation of the
transmission network by an independent system operator, procurement of new
generation capacity through competitive tender and different degrees of
competition at generation, wholesale or retail level or at more than one level.
8.The consultants' main finding in relation to the development
of a more competitive market structure in Hong Kong is that no major reforms of
the existing market structure are advisable until 2009 at the earliest since
there is no real potential for introducing competition at the generation level
before then. After that date, it would be possible to introduce competition
between generation companies and at the wholesale levels (particularly if the
electricity sector in Southern China has developed sufficiently to support
participation by power producers located in that area) and eventually at the
retail level.
9.The consultants consider that the introduction of competition
will require some reorganisation of the present structure of the industry.
Generation and transmission activities may have to be separated. Regulation in a
form different to the SCAs would be needed for transmission, distribution and
retailing activities. Different models could be introduced taking into account,
inter alia, developments and industry structure in the Mainland. However, the
consultants consider that the Single Wholesale Purchaser model, under which
competition is introduced between sellers of electricity at the generation
level, offers a common starting point for the different alternative paths.
Preliminary Views of the Energy Advisory Committee
10.The consultants' report and findings were put before the
Energy Advisory Committee1. Its preliminary views
are set out below-
-
the Study is an important first step by Government in
charting the future development of the electricity supply market in Hong
Kong. The consultants have stated their views on how such development should
proceed and the issues and constraints that will need to be addressed along
the way. It is clear however that substantial additional work is needed to
define in more detail the institutional and regulatory framework required to
support the development of future market structure envisaged by the
consultants and the transition path and time-frame. Although the existing
SCAs will not expire until 2008, the Committee considers it highly desirable
for the Government to map out the way forward early in order to enable
interested parties to prepare for any changes that may be introduced.
-
reliability of electricity supply is vital to Hong Kong's
interests, and that due consideration must be given to the maintenance of
reliable electricity supply when considering any major changes to the
present transmission system and regulatory and market structure.
-
whilst interconnection does not by itself bring about
competition, it would facilitate competition particularly where there are
multiple suppliers. The realization of the potential benefits of competition
would however hinge on the establishment of a suitable transmission grid and
supporting market and regulatory structure whereby competition in the supply
of electricity can be introduced to Hong Kong with participation of multiple
suppliers, including CLP, HEC and, in due course, electricity suppliers
based in Southern China. The Committee believes that this should be the
long-term objective.
-
the environmental impacts of various long and short term
options, including those arising from the different types of fuel used for
electricity generation under different options, would need to be evaluated
and taken into account when considering the way forward.
-
the economic benefits2
identified under the least cost scenario whereby joint planning by CLP and
HEC as one system involving increased interconnection are relatively small
compared to the present tariffs3 or the
potential long-term benefits that may be brought about by increased
competition under the scenario described in (c) above. It is important to
consider the Study in context to ensure that discussion on the long-term
development of increased interconnection and competition would not be
disproportionately overshadowed by the pursuit of relatively small
short-term benefits.
Way Forward
11.The consultants have made it clear that this is an initial
feasibility study and have recommended further detailed studies in a number of
areas. The Energy Advisory Committee has also pointed out that substantial
additional work is needed to define in more detail the institutional and
regulatory framework required to support the future market structure envisaged
by the consultants and the transition path and time-frame. The Government will
carefully examine the findings of the Study and conduct the necessary detailed
studies with a view to mapping out a way forward that is in the best interest of
Hong Kong.
12.Meanwhile, any views from interested parties are welcome.
Should you have comments on the Report, please send them to Economic Services
Bureau on or before 31 March 2000.
13.This paper, the Executive Summary of the Final Report and
the full text of the Final Report for the Study in MS Word 6.0 format may be
download by clicking the links below-
This
paper
Full text of
the consultants' Final Report
Executive Summary of the consultants' Final Report
Economic Services Bureau November 1999
Comments
1The Energy Advisory Committee advises the
Government on energy policy matters. Its membership is drawn from fields
relevant to energy supply, energy efficiency and conservation, environmental
protection and consumer interests.
2 The consultants have estimated that
the economic benefits of the least cost scenario would translate on average
across the two electricity companies into tariffs 0.4 cents/kWh less than those
under the base case in the period up to 2008.
3 According to the 1998 Annual Reports
of CLP and HEC, the average net tariffs of CLP and HEC for the year 1998 were
89.48 cents/kWh (before a special rebate of 1.82 cents/kWh) and 90.30 cents/kWh
respectively.
|